DBKL: Lift upgrades, replacement for low-cost housing started since 2020

 


Upgrading and replacement work for 306 lifts at People’s Housing Projects (PPR) and Public Housing (PA) projects have been conducted since 2020 and is expected to continue until 2024.

A statement from the Kuala Lumpur City Hall (DBKL) stated that the work, which is being conducted in phases, costs of RM169.6 million and will take another two years to finish.

“In addition to the replacement of lifts, scheduled maintenance and monitoring of lifts are conducted by existing contractors on site, who are also responsible should the lifts suffer damage,” the statement read.

According to the statement, the first phase involves 12 housing areas, PA Seri Kota, PA Seri Sabah 3A, PA Seri Sabah 3B, PPR Desa Petaling, PPR Salak Selatan, PPR Seri Anggerik, PPR Sg Bonus, PA Hang Tuah, PA Loke Yew, PA Seri Selangor, PPR Bukit Jalil 1 and PPR Bukit Jalil 2.

“A total of 104 lifts are being replaced and work will be completed by the end of this year,” the statement read.

Phase two will involve 109 lifts in 10 areas, PPR Raya Permai, PPR Seri Malaysia, PA Seri Perak, PPR Seri Alam, PA Kerinci 1A, PPR Kerinci, PPR Seri Cempaka, PPR Kg Muhibah, PPR Semarak and PA Seri Tioman.

Phase three will involve 18 lifts at PPR Desa Tun Razak and PA Seri Sarawak, while phase four will involve 48 lifts at PPR Batu Muda, PPR Laksamana, PPR Perkasa and PPR Pekan Kepong.

Phase five, meanwhile, involves three areas, PPR Bukit Jalil (Blok L,M,G & H), PA Seri Terengganu dan Seri Pangkor (1 & 2) with 27 lifts slated for replacement.

Batu MP P Prabakaran had earlier claimed that the project announced by Prime Minister Ismail Sabri Yaakob in October last year had yet to show any signs of starting.

Bernama