Deputy minister Abdul Rahman Mohamad says the projects are expected to be completed between February and March.

Deputy energy transition and water transformation minister Abdul Rahman Mohamad said the first project involved building a flood wall and installing a flap gate at Taman Rashna, at a cost of RM350,000.
It is scheduled for completion on March 17.
The second project entails building an outlet structure, installing a flap gate and constructing a flood wall near the Bukit Raja junction, at a cost of RM199,000. It is scheduled for completion on Feb 17.
“Third, a flood wall will be built at Taman Intan, at a cost of RM200,000. It is also scheduled for completion on Feb 17,” Bername quoted him as saying during a Dewan Rakyat special chambers session.
Rahman was responding to Azli Yusof (PH-Shah Alam), who asked about flood control plans for the Sungai Rasah basin following recent flash floods.
He said the department had also deployed six mobile pump units across four high-risk locations – Taman Rashna, Taman Intan, the area near the Bukit Raja junction, and the Aeon supermarket area – to accelerate floodwater drainage.
In the long-term, the government had approved an allocation of RM40 million under the first rolling plan of the 13th Malaysia Plan to build a water control gate at the mouth of Sungai Rasah, as well as a pump house, a flood retention basin and riverbank retaining walls.
“The project is currently in the preliminary design stage, with physical work targeted to commence in the second quarter of 2028 and expected to be completed by 2031,” he said.
Rahman said his ministry had also proposed splitting the RM40 million allocation into two separate tenders to accelerate the project’s implementation, potentially bringing forward its completion date to 2029.
He said a key focus would be preventing water from Sungai Klang from overflowing into high-risk areas in Shah Alam. - FMT