Pakatan brands MAHB as 'liars' over KLIA2 delay
Pakatan Rakyat had demanded that the Transport Ministry and Malaysia Airports Holding Berhad (MAHB) disclose the delay and cost of the construction of the new KLIA2 low cost terminal, which has been delayed indefinitely.
Petaling Jaya Utara MP Tony Pua and Lembah Pantai MP Nurul Izzah Anwar branded MAHB as "incompetent liars" for saying that the terminal will be completed by June this year in a statement released in March, only to state after the elections that it has been delayed indefinitely.
Pua pointed out that the cost of construction for the terminal - which was initially scheduled to be completed in September 2011 - had already escalated to RM4 billion in 2012 from RM1.7 billion when it was first announced.
"We won't be surprised if the cost reaches RM5 billion by the time it’s completed," Pua said, adding that he would not be surprised if the airport is actually completed only by June next year.
"They are missing the date here by at least six months," he further added.