ECRL is nearly 21pct complete, says Mohd Zuki

 


The East Coast Rail Link (ECRL) project which is expected to be completed in 2026 has reached a progress rate of nearly 21 percent so far, said Malaysia Rail Link Sdn Bhd (MRL) chairperson Mohd Zuki Ali.

Zuki (above) said although the percentage indicated that the project was ahead of schedule, it was still a long way to go, adding that there were several issues such as land acquisition and site clearance that needed to be solved.

“The most critical issue includes the approval from state governments on section A (Kota Bharu to Dungun), B (Dungun to Temerloh) and C (Temerloh to Port Klang) where we are still awaiting the approval from the Selangor state government.

"If we get the approval then the entire ECRL project will be able to be implemented (immediately) and to ensure that it does not fall behind schedule," he told reporters after visiting the Armed Forces Family Housing (RKAT) project site in Jeli today.

Also present was Minister in the Prime Minister’s Department (Economy) Mustapa Mohamed.

On the participation of local contractors in the ECRL project, Zuki, who is also the chief secretary to the government, said it had so far reached 12 percent of the 40 percent target set by MRL.

He added that more local contractors are expected to participate when the project’s civil works fully opened.

Bernama